The Ministry of Statistics and Programme Implementation (MoSPI) has released its July 2026 Flash Report.
The headline is not the ₹37.11 lakh crore pipeline. It is the concentration — and the completion gap — behind it.
Across 1,775 central sector projects above ₹150 crore, cumulative expenditure stands at ₹19.26 lakh crore, or 51.91% of revised cost.
Delivery is heavily front-loaded into transport. MoRTH carries 993 projects worth ₹9.62 lakh crore, while Railways adds 190 projects at ₹6.38 lakh crore. Transport and logistics account for roughly 70% of the pipeline by project count.
That concentration matters commercially. Road and rail EPC contractors, suppliers and lenders are not exposed to a diversified national programme — they are exposed to MoRTH and NHAI award cadence, land availability and payment cycles driving sector-wide cash flow.
The physical-versus-financial gap is the sharper signal. While 675 projects have crossed 80% physical progress, only 305 have crossed 80% financial completion.
The mismatch points to retention-heavy contracts, slow claim finalisation and milestone billing lagging physical output — a working-capital strain familiar to EPC balance sheets.
Cost revision is being normalised into baselines. The 735 mega projects carry an original cost of ₹28.77 lakh crore within a ₹37.11 lakh crore revised total, absorbing time and cost escalation rather than flagging it as exception.
The pipeline is still replenishing. July added 36 projects to PAIMANA-PROJ monitoring, including the ₹38,358 crore Meja Thermal Power Project Stage-II — the NTPC-UPRVUNL joint venture — and the ₹13,037.66 crore Jaipur Metro Rail Project Phase 2, run by Jaipur Metro Rail Corporation.
Commissioning continued with:
- GAIL (India) Limited's ₹2,810 crore Srikakulam-Angul gas pipeline
- NHAI's ₹2,298.37 crore Dwarka Expressway Package III
- The ₹2,069.6 crore Aligarh-Kanpur Package I highway
MoSPI’s monthly PAIMANA-PROJ cadence is converting central project delivery into a visible, data-driven governance layer.
Progress, cost and financial data are now systematically benchmarked — and the next Flash Report lands on September 25.
Insights

IRB Infrastructure Developers has signed a share purchase agreement to shift Solapur Yedeshi Tollway and CG Tollway out of its GIC-backed private InvI
3

The Supreme Court's NEEPCO v Astra Construction ruling confirms a contractual interest bar can strip pre-reference interest from arbitral awards, turn
3

NHAI and Sardar Sarovar Narmada Nigam Limited have signed a time-bound framework for National Highway, canal and pipeline crossings in Gujarat, waivin
3
GEt started for free
India's #1 construction management software with powerful features including site management, project bidding & marketplace


Powered by

© Tuskus 2025 - All Rights Reserved by Teamic Creative Lab Pvt. Ltd.