• Products
    Core
  • About us
  • Careers
  • News
  • Contact

insghits

BMC Fought an Eight-Month Road Contract for 28 Years

3
min

A 28-Year Delay, Dismissed

The Municipal Corporation of Greater Bombay lost Appeal No. 804 of 1999 on 5 May 2017, nearly 28 years after it awarded a percentage-rate contract to reconstruct Zakariya Bunder road.

Justices Anoop V. Mohta and P.R. Bora dismissed the Corporation's challenge to an award dated 22 June 1993.

The underlying dispute was small in scale: an eight-month contract period from 11 October 1989, delay in commencement, compensation claims. What matters is the duration, and who funded it.

The Arguments, and Why They Failed

Bharat Infrastructure & Engineering Pvt. Ltd. and Bharat Construction, the respondents, carried their award through a Single Judge and then a Division Bench.

Their counsel, M.M. Vashi instructed by M.P. Vashi & Associates, defended the arbitrator's findings on delay and contract interpretation. The Corporation's senior counsel Kevic Setalwad argued perversity and misconduct.

The bench held the arbitrator's reading was a possible view, therefore final under Section 30 of the Arbitration Act, 1940.

MCGB's legal team understood the standard. The appeal bought time, not outcome.

That standard was settled long before this appeal was filed. It is stricter still under Section 34 of the 1996 Act.

The Cost Not Entered in the Ledger

Run the file as the Corporation's law officer would have in 1994. The options ran the length of the ladder:

- Accept the 1993 award
- Challenge it under Section 30
- Appeal to a Division Bench

Payment deferral was the benefit. Senior counsel, a brief and two court tiers were the cost.

The cost not entered in the ledger: the award sum accrues interest while the file moves, and every bidder on the next MCGB road tender learns to load authority litigiousness into the rate above the schedule.

A Routine Job, a Recurring Template

Zakariya Bunder was a routine municipal reconstruction job. The litigation around it is the template.

Public authorities with volume arbitration exposure — municipal corporations, state road agencies, water boards — are the ones carrying this pattern. Their contract conditions on site handover and delay are drafted to shift risk onto the contractor, and then read against the authority at arbitration.

The Price of Asymmetry

Indian contractors price that asymmetry annually. It appears as a percentage above the estimate, as a contingency, as an unwillingness to bid the difficult ward.

Nobody itemises it, and it is real.

For contractors

An award against a municipal corporation is a receivable with an uncertain maturity date. Finance it accordingly, or decline the tender.

For authorities

Section 30 and Section 34 do not create optionality on delay.

They create a financing cost that reappears on the next tender, through a higher percentage rate and a thinner bidder list.

Insights

Explore More Insights

IRB Infra's 85% Profit Jump Rests on a 1.4% Margin

IRB Infrastructure Developers' Q2FY27 net profit rose 84.85% to ₹260.15 crore on 15% toll revenue growth and higher InvIT distributions.

2 min read

IRB Infra's 85% Profit Jump Rests on a 1.4% Margin

IRB Infrastructure Developers' Q2FY27 net profit rose 84.85% to ₹260.15 crore on 15% toll revenue growth and higher InvIT distributions.

2 min read

IRB Infra's 85% Profit Jump Rests on a 1.4% Margin

IRB Infrastructure Developers' Q2FY27 net profit rose 84.85% to ₹260.15 crore on 15% toll revenue growth and higher InvIT distributions.

2 min read

GEt started for free

Make better profits with each project.
Use Tuskus

India's #1 construction management software with powerful features including site management, project bidding & marketplace

CIN: U74103PN2023PTC221713

GST: 27AAKCT2315C1ZN

Company

About usCoreCareers

Quick Links

NewsContactPrivacy policyTerms of use

Powered by

©  Tuskus 2025 - All Rights Reserved by Teamic Creative Lab Pvt. Ltd.