NHAI issued the circular on Friday. Every contractor holding an awarded National Highway package now has a pricing decision it was not given time to make.
The land saving is genuine.
- Plazas are capped at eight lanes plus one over-dimension lane, with gantry-mounted RFID readers and ANPR cameras replacing the booth arrays that pushed some six- and eight-lane toll plazas past 30 lanes.
- Design throughput is fixed at 600 vehicles per hour per lane.
- Six-metre gantry clearance and variable message signs a kilometre upstream are now obligations, not options.
DPR-stage projects fold the layout into bidding documents. Awarded and under-construction projects adopt it, in NHAI’s language, through “changes in the scope of work.”
That phrase carries the exposure.
L&T, Dilip Buildcon, PNC Infratech and IRB Infrastructure price EPC and HAM packages against a plaza footprint sanctioned at bid stage.
Cutting lanes removes earthwork, pavement, booths and land. It adds gantry steel, electronics integration, and a completion interface the civil contractor does not control.
The tolling system is procured separately through IHMCL, NHAI’s tolling arm, on its own timeline.
A contractor can therefore be held to a completion date by a systems package that is neither in its scope nor in its price.
Two things follow for anyone bidding this quarter:
- Push gantry integration out of civil rates into a separately defined line item with its own completion test and delay remedy.
- Establish whether the eight-lane ceiling bites retroactively on concessions already carrying 20-lane plazas — the answer belongs in the bid, not in arbitration.
Revenue assurance is the larger unresolved item. Eight lanes at 600 vehicles per hour is a design assumption written into concession documents.
Indian corridors have not been observed at that rate under mixed traffic, partial FASTag penetration and over-dimensional freight.
Where throughput underperforms, queue spillback lands on the main carriageway and on the concessionaire’s revenue clock.
MoRTH has pursued free-flow tolling since the 2021 fee-rules amendment. NHAI has now converted that policy intent into a delivery obligation without rewriting the contracts built around the old plaza.
The signal for bid review: tolling has moved from a civil deliverable to a systems-uptime obligation.
The first MLFF variation schedule NHAI signs sets the reference price for NH awards well beyond this financial year.
Insights

IRB Infrastructure Developers' Q2FY27 net profit rose 84.85% to ₹260.15 crore on 15% toll revenue growth and higher InvIT distributions.
2 min read

IRB Infrastructure Developers' Q2FY27 net profit rose 84.85% to ₹260.15 crore on 15% toll revenue growth and higher InvIT distributions.
2 min read

IRB Infrastructure Developers' Q2FY27 net profit rose 84.85% to ₹260.15 crore on 15% toll revenue growth and higher InvIT distributions.
2 min read
GEt started for free
India's #1 construction management software with powerful features including site management, project bidding & marketplace


Powered by

© Tuskus 2025 - All Rights Reserved by Teamic Creative Lab Pvt. Ltd.