An estimate worth Rs 4.48 crore, a 5.07-km PMGSY-4 priority listing and Rs 10 lakh of murum surfacing, yet the Khaddi Khurd road stays impassable. The
insghits

The Allahabad High Court’s notices to the Centre, Uttar Pradesh Government, NHAI and the Ministry of Road Transport and Highways open a defect-liability phase for the 63 km Lucknow-Kanpur Expressway barely a month after its 13 July opening.
They place PNC Infratech’s concessionaire, Awadh Expressway Pvt Ltd, at the centre of the exposure.
The trigger was not one failure. Between 13 July and 11 August, depressions, subsidence and patchwork failure surfaced at around 45 locations on the 45 km greenfield section.
Surface slippage near Km 64 in Unnao appeared 13 days after opening. Viral footage of workers using pedestal fans to dry a waterlogged stretch near Begumkheda turned an engineering fault into a public accountability event.
What changes the liability equation is IIT Kharagpur’s early diagnostic direction.
Its field team collected 50 samples and found water seepage as deep as 18 feet, with missing drainage near Km 44.7 and settlement between Km 49 and 60.
The emerging conclusion — design and drainage inadequacy rather than isolated workmanship — is commercially significant.
Under concessionaire-led delivery, Awadh Expressway faces not just rework but a contest over whether design scope and monitoring were adequate at sanction stage.
That contest matters for the wider Hybrid Annuity Model pipeline. If defects are framed as design failure, liability migrates beyond a contractor’s built-to-specification defence and into concessionaire development and O&M obligations.
For listed EPC player PNC Infratech, exposure is threefold:
- Rectification cost inside the SPV
- Annuity and reputational risk with NHAI
- A pricing signal across its HAM order book
The deeper signal is institutional.
NHAI’s supervision and independent engineer checks did not catch a drainage deficiency that IIT Kharagpur identified within weeks.
Judicial scrutiny is now functioning as a backstop quality gate, with technical institutions deployed as forensic reviewers.
Concessionaires should expect design adequacy — not just construction compliance — to become a contested, bankable risk in future highway awards.
Insights

An estimate worth Rs 4.48 crore, a 5.07-km PMGSY-4 priority listing and Rs 10 lakh of murum surfacing, yet the Khaddi Khurd road stays impassable. The
3

More than 800 objections hit the Greater Bengaluru Authority within five days of a notice proposing the removal of 1,128 trees for the Hebbal tunnel.
4 min read

Deputy Commissioner Poonch Ashok Kumar Sharma chaired a September 25 review of bottlenecks on National Highway-144A, the strategic Akhnoor–Poonch corr
3
GEt started for free
India's #1 construction management software with powerful features including site management, project bidding & marketplace


Powered by

© Tuskus 2025 - All Rights Reserved by Teamic Creative Lab Pvt. Ltd.