Kupwara Bridge Case: ACB Chargesheets 10 After 15 Years

4 min
min

Nine public servants and one private contractor — in connection with alleged misappropriation of government store material, fraudulent release of security deposits, and financial irregularities in the construction of a steel bridge at Lastiyal-Kalaroose in north Kashmir's Kupwara district.

The Case

. The bridge carried a stipulated completion period of three months. Instead, the contractor began work after considerable delay, executed only a portion of the scope, and subsequently abandoned the project entirely.

and was never recovered after the abandonment.

, while bill deposits of Rs 81,400 were released despite outstanding government liabilities.

.

The Accused

The chargesheet names the full chain of accountability. Among those charged are:

, both retired Executive Engineers

, retired Assistant Executive Engineers

, Junior Engineer

, Assistant Accounts Officers

, Cashier

, Helper/Assistant Cashier

, Contractor

Industry Implications

, not just contractor default or isolated engineering negligence.

.

The message is unambiguous: legacy cases are being reopened, the full chain of signatories is in scope, and even small-value fraud can result in criminal charges.

, site inspection discipline, and contract enforcement clauses that should have triggered performance security forfeiture long before the ACB got involved.

Insights

Explore More Insights

Indian Railways, Gujarat to Fund Rs 166 Cr Alkapuri ROB

Indian Railways has approved a four-lane Road Over Bridge at Alkapuri in Western Railway's Vadodara division, with the Ministry of Railways and the Gu

3

NHAI Debarment Puts Independent Engineers on Notice

NHAI's two-year debarment of Theme Engineering Services over the Kanpur-Lucknow Expressway moves accountability from contractors to independent engine

4

Sidhi Road Protest Exposes PMGSY Last-Mile Delivery Gap

An estimate worth Rs 4.48 crore, a 5.07-km PMGSY-4 priority listing and Rs 10 lakh of murum surfacing, yet the Khaddi Khurd road stays impassable. The

3

GEt started for free

Make better profits with each project.
Use Tuskus

India's #1 construction management software with powerful features including site management, project bidding & marketplace

CIN: U74103PN2023PTC221713

GST: 27AAKCT2315C1ZN

Company

About usCoreCareers

Quick Links

NewsContactPrivacy policyTerms of use

Powered by

©  Tuskus 2025 - All Rights Reserved by Teamic Creative Lab Pvt. Ltd.