Deputy Commissioner Poonch Ashok Kumar Sharma chaired a September 25 review of bottlenecks on National Highway-144A, the strategic Akhnoor–Poonch corr
insghits

The Shivamogga–Tumakuru NH-69 four-laning corridor has moved past the point where the ₹6,400 crore headline matters. The operational question is now package-level execution spread.
The National Highways Authority of India (NHAI) is delivering the 214.43 km corridor under the Ministry of Road Transport and Highways (MoRTH) through the Hybrid Annuity Model (HAM), split into four packages to compress delivery. Three packages are effectively complete; the fourth, Bettadahalli–Shivamogga (56.33 km), is at 83.78% and holds the March 2027 completion date.
That asymmetry is the commercial signal.
- Package I — Mallasandra–Karadi (52.89 km): 100% complete and open to traffic.
- Package II — Karadi–Banavara (56.70 km): 99.98% complete.
- Package III — Banavara–Bettadahalli (48.51 km): 98% complete.
- Package IV — Bettadahalli–Shivamogga (56.33 km): 83.78% complete.
The corridor is not failing—it is exposing how HAM concentrates residual construction risk in the last active package.
Under HAM, NHAI pays 40% of bid project cost during construction and the balance as inflation-indexed annuities with interest over the operations period. Traffic risk stays with NHAI; construction and O&M risk sit with the private HAM concessionaires.
A package running 16 percentage points behind the corridor curve is therefore not just a schedule issue—it is a cash-flow timing issue. Annuity streams and completion-linked payments begin only at commercial operations date.
Delay on Package IV postpones the concessionaire's revenue while NHAI's liability clock keeps running.
For the corridor's catchment—Tumakuru, Hassan, Chikkamagaluru and Shivamogga districts—the route's integration with NH-48 at Tumakuru (toward Bengaluru) and at Shivamogga (toward Malnad and coastal Karnataka) determines freight and agricultural logistics.
Arecanut, paddy and industrial output moving toward Bengaluru gain time and reliability only when the divided carriageway, flyovers, grade separators and service roads are fully operational.
The infrastructure read: corridor-level percentages can mask package-level completion risk. NHAI's March 2027 target for Bettadahalli–Shivamogga is credible but not comfortable, with roughly 16% of work remaining in a monsoon-exposed window.
Exposure is uneven—NHAI and MoRTH carry funding and traffic risk, the unnamed HAM concessionaires carry delivery and delay penalties, and suppliers and logistics operators capture upside only after COD.
Insights

Deputy Commissioner Poonch Ashok Kumar Sharma chaired a September 25 review of bottlenecks on National Highway-144A, the strategic Akhnoor–Poonch corr
3

The Chakhesang Students Union has given NHIDCL 72 hours to terminate the contractor on the Chakhabama-Kikruma package of NH-29, with 44.30% physical p
4

Gurugram Metro Rail Limited has locked the alignment and access gates for the Subhash Chowk Metro station, but both entrances sit in a stretch that fl
4
GEt started for free
India's #1 construction management software with powerful features including site management, project bidding & marketplace


Powered by

© Tuskus 2025 - All Rights Reserved by Teamic Creative Lab Pvt. Ltd.