• Products
    CoreBids
  • About us
  • Careers
  • Pricing
  • Insights
  • Contact

insghits

Srinagar Ring Road: NHAI Faces Right-of-Way Reckoning

4 min read
min

The Srinagar Ring Road project has hit familiar terrain — not on the alignment itself, but in the paperwork, courtrooms, and utility corridors that determine whether an NHAI highway moves from notification to asphalt.

The Review Meeting

On Monday, Divisional Commissioner Kashmir Anshul Garg convened a review of Phases-II and II A in Ganderbal district. The agenda was not about engineering or cost overruns. It was about land — who owns it, who has been paid for it, who is still in court over it, and whose pipelines run through it.

The meeting, attended by Deputy Commissioner Ganderbal Jatin Kishore and NHAI's Project Director, surfaced the standard bottlenecks that seasoned infrastructure executives recognise immediately:

- Incomplete land handover from district administration to the executing agency
- Unresolved compensation disputes now sitting in court references
- Government buildings awaiting demolition on an Equal Value Infrastructure (EVI) basis
- A PHE water pipeline that cannot be shifted without disrupting Srinagar's municipal supply

Garg's directives were operationally precise:

1. Compile comprehensive land acquisition documentation by Friday
2. Conduct a joint site inspection on Saturday
3. Expedite tree removal with transplantation and compensatory afforestation
4. Resolve private structures on state land using NHAI's compensation framework

The EVI Mechanism: A Hidden Risk

The commercial layer is worth watching. The EVI mechanism — where NHAI must build equivalent government infrastructure before demolishing existing structures — creates a parallel works programme that contractors rarely price into their bids with precision.

It also transfers execution risk from the district administration to the highway authority, compressing NHAI's delivery timeline without expanding its control over pre-construction variables.

Impact on Contractors

For the unnamed contractor executing these phases, the delay signals are material. Right-of-way delays extend project duration, inflate indirect costs, and trigger claims. In J&K, where working seasons are already compressed by geography and weather, every month lost to administrative clearance is a month that cannot be recovered on site.

A Structural Signal for NHAI

The deeper signal is structural. When a Divisional Commissioner — a senior administrative officer — must personally direct land handovers and pipeline relocations for a national highway project, it indicates that standard NHAI-district coordination mechanisms are insufficient for sensitive geographies.

This is not unique to Kashmir. Similar patterns play out across Uttarakhand, the Northeast, and parts of the Western Ghats, where land records are fragmented, litigation rates are high, and utility infrastructure is densely layered through urban and peri-urban corridors.

For contractors and consultants working in such geographies, the takeaway is clear: bid durations must bake in administrative resolution cycles, not just construction sequences.

And for NHAI, the repeated reliance on administrative escalation suggests the authority's pre-construction processes need strengthening — particularly around land acquisition handover protocols and inter-departmental utility shifting agreements — before financial closure is declared and contractors mobilise.

Srinagar's ring road will eventually be built. The question is whether the industry learns something from how it gets unblocked.

Insights

Explore More Insights

HC's National-Importance Doctrine Unlocks Bullet Train Power Link

The Bombay High Court has cleared mangrove felling for MSETCL's 13-km transmission line serving the Mumbai-Ahmedabad bullet train corridor, establishi

4 min

Kondapochamma Sagar: Vigilance Commission Pushes ACB Probe into ₹2,898 Crore Reservoir Irregularities

The Telangana State Vigilance Commission has recommended an Anti-Corruption Bureau investigation into the Kondapochamma Sagar Reservoir project after

6 min read

Dilip Buildcon Lands ₹160 Cr Odisha Diversion Road EPC

Dilip Buildcon Ltd. has secured a ₹160.20 crore EPC contract from the Odisha Bridge & Construction Corporation for a six-lane diversion road in Sundar

6 min read

GEt started for free

Make better profits with each project.
Use Tuskus

India's #1 construction management software with powerful features including site management, project bidding & marketplace

CIN: U74103PN2023PTC221713

GST: 27AAKCT2315C1ZN

Company

About usCorePricingCareers

Quick Links

InsightsTendersAllotmentContactPrivacy policyTerms of use

Powered by

©  Tuskus 2025 - All Rights Reserved by Teamic Creative Lab Pvt. Ltd.