The Chakhesang Students Union has given NHIDCL 72 hours to terminate the contractor on the Chakhabama-Kikruma package of NH-29, with 44.30% physical p
insghits

The prolonged stall on NH 29 Package II has moved from a delivery problem to a termination fight.
The Eastern Nagaland Sumi Students’ Union (ENSSU) has now joined the Chakhesang Public Organisation (CPO) in demanding that the National Highways & Infrastructure Development Corporation Limited (NHIDCL) terminate Ratna Infrastructure Projects Pvt. Ltd. and appoint a replacement agency for the Chakhabama–Kikruma two-lane stretch on the Kohima–Jessami corridor.
Originally tendered in 2019 and scheduled for completion by June 30, 2022, the package is now years past deadline.
ENSSU president Vihepu K Yeptho and general secretary Gihuka V Chophy have framed the delay as an accountability failure, not merely a construction shortfall.
The CPO’s move toward a Public Interest Litigation before the Gauhati High Court, Kohima Bench turns public frustration into a formal legal lever.
The contractor is the immediate exposure point. Ratna Infrastructure Projects Pvt. Ltd. faces termination, potential forfeiture of performance security and exclusion from any replacement procurement.
NHIDCL carries a separate oversight risk: it is now publicly accused of accepting repeated assurances without visible progress on a strategically vital corridor.
The alignment serves Kiphire and Shamator districts, where residents are pushed onto lengthy Zunheboto diversions. That geography drives high mobilisation and logistics costs and thin productivity for any contractor—factors that explain the stall but do not excuse it.
A replacement agency will inherit:
- A difficult alignment
- Weakened schedule assumptions
- A compressed window toward the September 2026 timeline
This is no longer a routine NHIDCL delay. Student unions and public organisations in the Northeast are using judicial pressure to force contract termination and re-procurement.
For contractors bidding remote border corridors, the risk calculus has shifted: delays now carry organised, legally backed termination exposure, and underperformance can no longer be absorbed by administrative inertia.
Insights

The Chakhesang Students Union has given NHIDCL 72 hours to terminate the contractor on the Chakhabama-Kikruma package of NH-29, with 44.30% physical p
4

Gurugram Metro Rail Limited has locked the alignment and access gates for the Subhash Chowk Metro station, but both entrances sit in a stretch that fl
4

NHAI has debarred PNC Infratech from its tenders for three years and, critically, extended the penalty upward from the Awadh Expressway concessionaire